Following are some points from Harry’s talk; a more
detailed account about the hydro-installation is in
his article in
newsletter 128 (spring 2020).
The site:
It was Sherborne (Corn) Mill, an original mill site
dating back to Domesday. The 1797 mill was in
ruins; the bypass tunnel, control sluice, and wheel
pit remained but in poor condition. The mill pond
was full of silt and reeds.
Why rebuild the mill?
The
earth dam was unstable and so a retaining wall was
required; the retaining wall needed to be L shaped,
and piled, given the poor soil condition; water was
flowing through the middle of the site anyway.
The wheel:
Overshot, 3.8m diameter steel constructed as a
specialised one-off by Smith Engineering of Maryport,
Cumbria. It is rated at 3.4Kw at 8rpm. It was
commissioned in 2018.
Fundamental learnings:
· A Dutch Archimedes screw was considered, but
it would have been ugly, dangerous, and too
expensive.
· Overshot is a great choice because of its
high efficiency in turning potential energy into
kinetic.
· Climate change will change things in the
lifetime of the installation.
· Do not undersize your waterways – multiply
by a factor of 4 from the maximum known flows.
· The bureaucracy is overwhelming – to some
extent do it first and then seek forgiveness rather
than permission upfront.
Site-specific considerations:
· It is spring water which deposits limescale
– this protects but clogs. There is as much as one
inch of deposition per year.
· Think about the run-off in your catchment
area from newly built hard surfaces from new
house-building.
· A mill pond will gather silt; it’s a dam.
· Following the collapse of Toddbrook
Reservoir’s dam in Whaley Bridge, there are new
restrictive rules for dams of certain size
reservoirs, and they now require inspection.
Fortunately this one is small and exempt.
Mechanical learnings:
· The torque involved is colossal.
·
Do not weld anything – flexing will cause
propagation of the inevitable microscopic cracks in
welds.
· Mechanical devices wear and fail – have a
maintenance routine and a budget.
· Ensure there is a designed break point, such
as the rubber coupling in this case.
· Gearbox cooling is required. There is a
mechanical fan!
· Safety is a factor.
Things
that worked:
· Spherical roller bearings; they are
bombproof; the Brevini Italian-made gearbox; the
electric synchronisation box from Sustainable
Control Systems; home-made automatic electric
control actuator (using hospital bed parts!) for
moving the sluice gate.
Things
that didn’t:
· Dunlop tyres for the break point – use
genuine Fenner-flex.
· The undersized shaft, originally 80mm,
replaced by 100mm.
· Keyed or welded connections between the hub
and shaft, replaced by a new hub connection – a
radial wedge with B-loc compression fittings. The
failing welds were the cause of a catastrophic
failure in January 2023.